Symmetra Extended Frame Installation

Solved
jrc4728_apc
Crewman
Crewman
0 Likes
2
66

Symmetra Extended Frame Installation

This was originally posted on APC forums on 1/22/2008


I have a SXR12B12 Symmetra Extended Frame to be installed on a UPS-APC-SY12K. Can this be installed "hot" (power on and under load) or do I need to shut down the Symmetra and remove power first?


Accepted Solutions
jrc4728_apc
Crewman
Crewman
0 Likes
0
66

Re: Symmetra Extended Frame Installation

This was originally posted on APC forums on 1/22/2008


Thanks!

See Answer In Context

2 Replies 2
EZ_Button_apc
Commander
Commander
0 Likes
0
66

Re: Symmetra Extended Frame Installation

This was originally posted on APC forums on 1/22/2008


The XR frame can be attached while the UPS is running. You will not need to power anything off.

jrc4728_apc
Crewman
Crewman
0 Likes
0
67

Re: Symmetra Extended Frame Installation

This was originally posted on APC forums on 1/22/2008


Thanks!